Building 57 – Kingsley Green, Radlett

Building 57 had been left abandoned and unused for approximately 10 years prior to the arrival of main contractor Osbourne’s who used the building as there project office while construction works were underway at Kingfisher Court.

As part of the agreed planning permission for Kingfisher Court, it was stated that once construction works were completed, Building 57 would be demolished.

The local authority was notified of the impending works as required under section 80 of the Building Act 1984.

Step 1: A Building Survey
In survey of buildings for demolition, following process is carried out:

  • Types of construction material used
  • Usage of building prior and present during demolition.
  • The presence of wastewater, hazardous materials, matters arising from toxic chemicals, flammable or explosive and radioactive materials, etc.
  • Drainage conditions and possible problems on water pollution, flooding and erosion.
    Shared facilities with adjoining building, including common staircases, partition walls.
  • Adjoining pedestrian and vehicular traffic conditions
  • The sensitivity of neighbourhood with respect to noise, dust, vibration and traffic impact.

Step 2: A Structural Surveying
In structural survey, following process are involved in demolition:

  • The method of construction
  • The structural system and structural conditions of basements, underground tanks or underground vaults.
  • The original structural system employed in the design.
  • The condition of the building.

Step 3: Preparation of Demolition Plan for Structures
A detailed demolition plan is made which illustrates the different process involved and they are:

  • The location of the building to be demolished.
  • The distances from the building to be demolished to its adjacent buildings, streets, structures and significant street furniture.
  • The structural support systems of the building.
  • A plan showing the procedure for the demolition of the building; detailed sequence of demolishing structural members; and the method of demolition to be adopted.
  • A plan showing all precautionary measures for the protection of the public including hoardings, covered walkways, catch platforms, catch fans, scaffolding, protective screens and safety nets.
  • Method of handling demolished building debris.
  • Time required for the complete demolition process etc.

The scope of work also involves a full invasive asbestos survey and the removal of ACM’s from pipework and associated service ducts.

The project was procured using the Minor Works JCT building contract 2016 with contract duration of twelve weeks.

Website: www.hpft.nhs.uk

NHS Trust

£200k

You must be logged in to post a comment.