Blu Building Consultants Holly Lodge existing courtyard
Blu Building Consultants Holly Lodge foundation and link
Blu Building Consultants Holly Lodge crane front
Blu Building Consultants Holly Lodge crane lift
Blu Building Consultants Holly Lodge new modular building
Blu Building Consultants Holly Lodge modular building inside
Blu Building Consultants Holly Lodge modular building external
Blu Building Consultants Holly Lodge new modular building path view
Blu Building Consultants Holly Lodge existing courtyard

Holly Lodge Modular Building Staff Welfare Facility

In October 2019 we were appointed to complete a feasibility on the provision of additional staff welfare facilities to the existing Adult Community Mental Health Services at Holly Lodge in Cheshunt.
The existing building was listed therefore careful consideration was required to review all the potential options to maximise gain for the service. Due to the listed building implications local authority planning approval was a key consideration. After some initial architectural space planning studies it was clear that there was only one available location for any additional ground floor footprint to create the necessary additional space for staff welfare facilities, this being an existing courtyard.

Leave a Reply

Your email address will not be published. Required fields are marked *

Fill out this field
Fill out this field
Please enter a valid email address.
You need to agree with the terms to proceed